Falcon Contracting Co. in Columbus will begin milling Military Road, Seventh Street North and Willowbrook Road today.
The work on Military will run from Third Avenue North to 18th Avenue North. Seventh Street will be milled from 18th Avenue to Willowbrook, and Willowbrook will be milled from Seventh Street to Hospital Drive.
Each street will be milled 1.5 inches below curb and gutter levels before paving begins.
Doug Phillips, with Falcon Contracting, said Military will be milled first. A paving crew will begin working on Military when the milling crew moves on to Seventh Street and Willowbrook.
Phillips estimates the milling will take two weeks to complete, followed by paving. The newly paved streets will be striped two weeks after being paved.
Work is scheduled to begin around 8 a.m. each morning following school traffic.
You can help your community
Quality, in-depth journalism is essential to a healthy community. The Dispatch brings you the most complete reporting and insightful commentary in the Golden Triangle, but we need your help to continue our efforts. In the past week, our reporters have posted 26 articles to cdispatch.com. Please consider subscribing to our website for only $2.30 per week to help support local journalism and our community.
You can help your community
Quality, in-depth journalism is essential to a healthy community. The Dispatch brings you the most complete reporting and insightful commentary in the Golden Triangle, but we need your help to continue our efforts. In the past week, our reporters have posted 26 articles to cdispatch.com. Please consider subscribing to our website for only $2.30 per week to help support local journalism and our community.